Rough-in work is moving along at Fermilab 13th Floor Renovation. Sherman Mechanical has been running ductwork and Valley Electric is installing cable trays that should be completed by next week....
Fox Metro Building “W” Construction Update
Construction at the Water Treatment Building at Fox Metro continues to move forward. Concrete footings and foundation walls have been completed. Underground plumbing work has started. Underground...
Fox Valley Park District: Blackhawk Park Rendering
Check out this rendering of Blackhawk Park. R.C. Wegman is very excited to be working on this project with the Fox Valley Park District. Construction is underway and going well on the site and the...
Robert C. Wegman Way: Street Dedication
Aurora, IL honors R.C. Wegman founder Robert C. Wegman for his dedication to Aurora. The street dedication and sign unveiling ceremony was held on Saturday, June 17 at 11:00 a.m. at the corner of...
Rush Copley Medical Center Parking Garage Addition
The Rush Copley Medical Center Parking Garage Addition has gained occupancy from the city, and the hospital employees are happy to have the expanded garage to park in now.
Aurora Fire Station #7 Construction Update:
Construction continues on schedule at the new Aurora Fire Station #7 as Kevin Nugent Construction sets the formwork and steel reinforcing for the footings with plans to pour concrete by the end of...